Keith Butterfield, Yacht and Marine Surveyor. Costa del Sol, Spain.

According to the type and age careful preparations need to be taken to support the hull during lift, placement on blocks and during subsequent repairs. Any weakening of hull structure by removal of skin plating and/or structural members during repairs are accounted for, and supporting blocks/frames/measures are put in position to avoid deformation.

Carry out an external inspection of the hull, equipment and machinery so far as is necessary and practical to determine the general condition prior to repairs commencing. Older ships of certain types may also be subject to a general examination of some specified internal areas of the hull. The aim is to assess suitability to undergo remedial repairs. If a surveyor identifies corrosion, structural defects or damage not previously noticed, which in the opinion of the surveyor affects the vessels ability to undergo planned remedial measures, then additional measures, recommendations or conditions are to be specified.

The examination of the hull, detailed checks of selected parts and any repairs may be supplemented with NDT measurements where deemed necessary. The tests and measurements will be witnessed by the surveyor where applicable. Many aspects are similar to the requirements of new build vessels, for instance the repairers ability to carry out the remedial task. However the concern prior to commencing repairs is the suitability of the materials to be used during the repair. Checks need to ascertain that all materials accord with, or are compatible with those used in the original construction.

The requirements and suitability of all welding equipment and consumables need checking, as above, along with the coding of the welder/fabricator. Where jigs are necessary to ensure fit-up the surveyor must attend to the final fit-up and check that dimensions, gaps, weld groove preparation, filler material etc. are suitable. Visual inspection of all hull welds is necessary with specific areas of the new plate inserts/structural members identified for particular NDT, depending upon the metal used. The dimensions and thickness of inserts/ribs are to be calculated by relevant scantling rules, all corners to be suitably radius’ed. All testing and results are to be overseen and if the yards NDT equipment is used calibration certificates are to be provided.

Upon completion of repair all exposed surfaces are to receive paint protection where required. Surfaces are to be prepared appropriately, (usually grit blasting), and the correct primer and final coat applied promptly. The correct antifouling to metal type is to be used.